Purpose:
This document defines all major aspects of the project and forms the basis for its management and the assessment of overall success.
There are two primary uses of the document:
To ensure that the project has a complete and sound basis before there is any major commitment to the project
To act as a base document against which the project can assess progress, change management issues, and ongoing viability questions.
For construction projects, the content of the Project Initiation Document is set out in the Project Execution Plan.
Fitness for purpose checklist:
Does the document correctly represent the project? Does it show a viable, achievable project that is in line with corporate strategy, or overall programme needs? Is the project organisation structure complete, with names and titles? Have all the roles been considered? Does it clearly show a control, reporting and direction regime that is implementable, and appropriate to the scale, business risk and business importance of the project? Is the project organisation structure backed up by agreed and signed job definitions? Are the relationships and lines of authority clear? Does the project organisation structure need to say to whom the Project Board reports? Do the controls cover the needs of the Project Board, Project Manager and Team Managers? Do the controls satisfy any delegated assurance requirements? Is it clear who will administer each control?
Suggested content:
Source information:
Notes:
The Project Initiation Document will need to be formally approved and signed off by the Senior Responsible Owner at the end of the initiation stage of the project. It is typically assembled by the Project Sponsor/Project Director and parts of it may be updated and refined throughout the project life cycle up to and including project closure.
The Project Initiation Document is not necessarily one document, but can be a set of documents. It is likely to be developed through several reiterations. It will have stable elements and dynamics ones which will need to have new versions created as the project progresses.
Ensure that the presentational aspects of the Project Initiation Document are thought through. The complete product can be large when all the detailed Product Descriptions and job definitions are included. It can be daunting to receive the whole document, and in some circumstances this could be counterproductive. Use appendices to hold the detail and only publish these when requested.
In the context of OGC construction related projects the PID or its equivalent should be co-ordinated and owned by the Project Owner with much of the content being provided by the project sponsor, manager, team or external parties as required.
Further information:
See the briefing: Project management; see also document outlines for project brief, project plan and project execution plan.
Managing Successful Projects with PRINCE 2