Purpose:
The purpose of the Project Initiation Documentation is to define the project, in order to form the basis for its management and an assessment of its overall success. The Project Initiation Documentation gives the direction and scope of the project and (along with the Stage Plan) forms the 'contract' between the Project Manager and the Project Board.
The three primary uses of the Project Initiation Documentation are to:
The Project Initiation Documentation is a living product in that it should always reflect the current status, plans and controls of the project. Its component products will need to be updated and re-baselined, as necessary, at the end of each stage, to reflect the current status of its constituent parts.
The version of the Project Initiation Documentation that was used to gain authorisation for the project is preserved as the basis against which performance will later be assessed when closing the project.
Fitness for purpose checklist:
Suggested content:
As a minimum the documentation should answer the following fundamental questions about the project:
The Project Initiation Documentation has to answer the above questions to a sufficient level of detail to maintain control of the project. There follows a contents list for the Project Initiation Documentation. Note that the first two (project definition and project approach) are extracted from the Project Brief.
Project definition, explaining what the project needs to achieve. It should include:
Project approach, to define the choice of solution that will be used in the project to deliver the business option selected from the Business Case, taking into consideration the operational environment into which the solution must fit
Business Case, describing the justification for the project based on estimated costs, risks and benefits
Project management team structure, a chart showing who will be involved with the project
Role descriptions, for the project management team and any other key resources
Quality Management Strategy, describing the quality techniques and standards to be applied, and the responsibilities for achieving the required quality levels
Configuration Management Strategy, describing how and by whom the project's products will be controlled and protected
Risk Management Strategy, describing the specific risk management techniques and standards to be applied, and the responsibilities for achieving an effective risk management procedure
Communication Management Strategy, to define the parties interested in the project and the means and frequency of communication between them and the project
Project Plan, describing how and when the project's objectives are to be achieved, by showing the major products, activities and resources required on the project. It provides a baseline against which to monitor the project's progress stage by stage
Project controls, summarizing the project-level controls such as stage boundaries, agreed tolerances, monitoring and reporting
Tailoring of PRINCE2, a summary of how PRINCE2 will be tailored for the project.
Source information:
Project Brief
Discussions with user, business and supplier stakeholders for input on methods, standards and controls.
Notes:
The Project Initiation Documentation will need to be formally approved and signed off by the Senior Responsible Owner at the end of the initiation stage of the project. It is typically assembled by the Project Sponsor/Project Director and parts of it may be updated and refined throughout the project life cycle up to and including project closure.
The Project Initiation Documentation is not necessarily one document, but can be an index for a collection of documents, a document which cross-references to a number of other documents or a collection of information in a project management tool. It is likely to be developed through several reiterations. It will have stable elements and dynamics ones which will need to have new versions created as the project progresses.
Ensure that the presentational aspects of the Project Initiation Documentation are thought through. The complete product can be large when all the detailed Product Descriptions and job definitions are included. It can be daunting to receive the whole document, and in some circumstances this could be counterproductive. Use appendices to hold the detail and only publish these when requested.
In the context of OGC construction related projects the Project initiation documentation or its equivalent should be coordinated and owned by the Project Owner with much of the content being provided by the project sponsor, manager, team or external parties as required.
Further information:
See the briefing: Project management; see also document outlines for project brief, project plan and project execution plan.
Managing Successful Projects with PRINCE 2