The Procurement Process

9 Proposal Evaluation

Procurement Principals
0 Procurement Principals 1 Project start-up 2 Risk Allocation Model 3 Business Case 4 Procurement Strategy 5 Market Assessment 6 Market Creation 7 Produce Requirement 8 Supplier Selection 9 Proposal Evaluation 10 Contract Preparation 11 Bid Evaluation 12 Award 13 Project Closure 14 Implementation / Transition 15 Contract Management
Back Next
 

You are on step 7 of 8 steps.

Click for slide: Issue requirement and draft contract Click for slide: Evaluate proposals Click for slide: Check technical implications Click for slide: Evaluate variant bids Click for slide: Select suppliers Click for slide: Update the business case Click for slide: Produce evaluation report Click for slide: Notify and debrief unsuccessful suppliers
Previous step Next slide

What you need to do

Produce an evaluation report setting out the results of the evaluation and recommending the suppliers to be invited to take part in the next stage of the procurement.

Seek approval from decision maker(s) (SRO, who may consult the project board) to proceed.

Points to consider

The Evaluation Strategy briefing has a suggested content for the evaluation report.